CANTON – Town and village officials continue to explore options for a new or renovated Canton Municipal Building.
At a recent joint meeting, Deputy Mayor Anna Sorensen reported that the joint building committee has met on numerous occasions with a focus on storage use.
She said the committee has met with town, village and court clerks with the premise that storage space can be reduced substantially that could reduce construction costs..
According to meeting minutes, Sorensen also stated that the building committee has been working with a group of Clarkson University students who have been tasked to come up with a plan, basic layout and suggestions on a new municipal building.
These students are immersed in a capstone class, she noted, meaning the group will be working specifically on the next steps of refining the plans and providing the committee with new ideas.
Sorensen also pointed out that a declining equalization rate is impacting what the village can potentially borrow for a municipal building project.
Town Councilman John Taillon said the Development Authority of the North Country (DANC) will be represented at the next building committee meeting to discuss possible funding sources for such a project.
In April 2023, both boards were introduced to a design by BCA Architects and Engineers, Watertown, for a new building at a cost of more than $25 million. Both boards agreed the price tag was too expensive.
During public comment, Canton resident Toby Irven informed elected leaders that the Capital Resource Corporation could provide some resource for funding for a new municipal building and that the corporation “stands ready to engage with the town and village.”
In other matters at the Feb. 7 joint meeting, Town Supervisor Mary Ann Ashley updated both boards on the Comprehensive Plan oversight initiative shared by both boards.
Ashley said a kickoff meeting was held Nov. 28 and the next steps will see Jackie Hakes, director of planning services for M.J. Engineering, sending additional information to department heads seeking recommendations on priorities for 2024 and 2025.
In March 2023, the two boards agreed to split the cost of $8,900 to M.J. Engineering to assist in keeping the Canton Comprehensive Plan on track.